Drilling for Water
GETTING THE BUILDING-
BALL ROLLING
STARTING WITH A WELL
In the fall of 2021 we hired a well-driller. We had no idea it would take so many months to actually get a well. Plus, the cost of the well had increased 25% from pre-pandemic estimates. Additionally, we had to put in a gravel road for their heavy equipment, a $30K expense for which we had not planned.
First we had the path to the well site widened in the fall of 2021. But this, we were told, was not enough.
When the digging rigs showed up on May 26, Butch hopped a plane so he could see it for himself.
It took several days to finally reach it, but on June 1, 2022 we finally found water at 366 feet deep.
TA-DA!!
After eight months and tens of thousands of dollars we got our well.
But we still haven't tasted the water!